Approve timesheets

Check the week’s timesheets on the web or the iPhone, or a pay period or any run of days on the web, approve the ones that are waiting, and take an approval back.

Who can do this: Anyone with “Approve clock-ins” (Supervisors, Location Managers and Admins by default) or “Approve timesheets” (Location Managers and Admins by default; a Supervisor can be given it).

Web and iPhoneChecked

On this page

There is one timesheet per shift worked: the clock-in, the breaks and the clock-out together. A timesheet with nothing unusual about it is approved by itself and shows Approved with “· auto”. The ones marked To approve were flagged for a reason, shown beside them.

What the flags mean

  • In late, In early: clocked in more than 15 minutes after or before the shift’s start, with the minutes.
  • Left early, Ran over: clocked out more than 15 minutes before or after the scheduled end.
  • The 15 minutes is the site’s own setting, and so is how far past the clock-in circle counts as Off site. See Clock in away from the site.
  • Not on rota: no shift on a published rota to match it to.
  • Off site, with the distance, and Location off: see Clock in away from the site.
  • Forgot to clock out: they were clocked out automatically. See Fix a forgotten clock-out.
  • By a manager: a time was entered or corrected by a manager.

Each finished timesheet also has a break mark, such as Break 25m ✓ or No break · 7h. Approving one with a short or missing break asks once: Fix or Approve anyway. See Check breaks on timesheets.

On the web

Go to Rota & team, then Timesheets

  1. Pick the location in the sidebar, and the week with the arrows at the top. If it says a number to approve in other weeks, press that bar to jump to the earliest one. To see more than a week at once, see below.
  2. Press the To approve filter to see only what is waiting. The list on the left narrows it to one person. The amber keys above the list count the week’s flags by kind, such as In late 3 or Ran over 5: press one to see only those, and again to see all. The Flags filter lists the same kinds.
  3. Click a row to open the timesheet. On the left are the hours worked against the rota; on the right is what was recorded: the times under Clocked, how far from the site, the map under Where, the Photo if your site takes one, and the History.
  4. If a time is wrong, correct it first. Then press Approve, or Approve and next to go straight to the next one waiting. It says Approved.

You do not have to open each one. Each waiting row has its own Approve button, and Approve all, with the count, approves everything waiting in the list as filtered. The bar above the list always shows Approve, Change person and Delete: tick rows, or the box in the heading for all of them, and each button shows how many of the ticked rows it applies to, such as Approve 3.

On the phone

  1. Open Team and choose Timesheets. From Hub, the Clock-ins row marked “to approve” goes to the same place. An inbox item headed Clock-in to approve opens that timesheet directly.
  2. Step to the week with the arrows and choose To approve.
  3. Tap a timesheet to see what was worked, the rota, the clock times, the map and the photo. Press Approve. It says Timesheet approved.
  4. To approve everything waiting in the list, press Approve all, then Approve when it asks.

See a pay period or any run of days

On the web the page can show more than a week, so you can check and correct a whole pay period before you export it. Press the dates between the arrows at the top of the page:

  • Week: one week, as before. With a run of days on show it reads This week and goes back to the week under way.
  • This pay period and Last pay period, with their dates: shown once the location has a pay period.
  • Any other days: press a first day on the calendar, then a last day. A run can be up to 92 days, and days further than that from the first one are greyed out.

The list, the totals, the filters, the ticked-row buttons and Approve all then cover all of those days. The list is grouped a person at a time, each with their count of timesheets, hours and (if you can see pay) pay; the Group menu changes that. Someone on a salary shows Salary in place of pay. The arrows step to the run of days before or after, and a pay period steps to the next pay period. The days are kept in the page’s address, so a link to it opens the same days. Timesheets waiting on other days are counted on a bar that says to approve outside these days. Export opens set to the days on show. On the phone the list is a week at a time.

What happens next

The timesheet shows Approved, and under that heading who approved it and when. Only approved timesheets go into the payroll export. Approving does not lock anything: someone with the edit permission can still change the times, and the timesheet is then marked Edited.

Take an approval back

Press Un-approve: on the row or at the foot of the open timesheet on the web, or at the foot of the timesheet on the phone. On the web you can also tick several approved rows and un-approve them together. The timesheet goes back to To approve with its hours as they were, and nobody is told. If it had already gone out in an export it says Already exported, so you know payroll was sent something that no longer stands.

If it doesn’t work

The page lists hours per person and has no Approve buttons
The sidebar is set to all locations. Pick one location to approve its timesheets.
A shift nobody clocked in for is missing from Timesheets
The rota for that week was never published. A shift nobody clocked into is listed as Absent only once its week’s rota is published. If you can edit the rota, the page says Rota not published with how many shifts are not shown: press that bar to open the week’s rota, and publish it.
You can see timesheets but there is no Approve button
You have “See timesheets and clock-ins” but neither approving permission. An Admin can switch on “Approve clock-ins” or “Approve timesheets” for you.
Approve is greyed out in the open timesheet
You have changed a time or the break and not saved it. Press Save or Reset on the bar at the foot of the panel first.
“Still on shift — nothing to approve yet”
They have not clocked out. Wait, or set an end time to clock them out.
“Deleted — restore it first”
The timesheet was deleted. Open it and press Restore, then approve it.
“That timesheet has changed. Look again.” or “No longer approved.”
Someone else changed or un-approved it after your list was drawn. Look at it again as it now stands.

Was this the right page?